Hi guys,
These are no doubt a real beginner’s question, I know …
In the Server Trigger hookup guide it shows suggested wiring configuration for multiple trigger boards (“star power” configuration).
I’d like to understand what the switch wiring looks like in this sort of configuration, where I just want to have a single switch that controls all of the boards at the same time. Similarly, what if I had multiple boards that each had their own power supply - can I use a single switch to control all of those boards at the same time?
Thanks in advance.
Cheers, Craig